Do not defer reporting until 2027
Article 14 reporting has applied to manufacturers since 11 September 2026. If the process is not operating yet, set up ownership and backup, awareness records, the relevant coordinating CSIRT and the SRP handoff now. The main CRA requirements apply from 11 December 2027. The monthly actions below are planning milestones, not statutory deadlines.
Q1 — scope, risk and assessment route
Outcome: agreed product boundary, work plan and assessment route.
- January — inventory products, versions and variants sold in the EU, remote functions and supply-chain roles. Record market placement for legacy releases and assess substantial modifications separately.
- February — assess cybersecurity risk, map applicable Annex I requirements and assign owners and due dates to gaps.
- March — confirm classification and the Article 32 route. If a notified body is needed, confirm the scope and start discussions now.
Q2 — controls and support
Outcome: operational vulnerability handling and evidence linked to releases.
- April — address priority control and secure-default gaps and test the changes.
- May — link the SBOM to the release artefact and review supplier evidence and dependency coverage gaps.
- June — document the support period, rehearse reporting and verify safe updating and recovery.
Q3 — technical file and release rehearsal
Outcome: a draft technical file, test evidence and a list of open decisions.
- July — assemble the Annex VII technical file and Annex II user information.
- August — rehearse the release: test results, SBOM, artefact integrity and proof of update delivery.
- September — have someone independent of evidence preparation review it, close critical gaps and confirm the conformity assessment schedule.
Q4 — conformity, release and support
Operational goal: allow time before 11 December for assessment outcomes, remediation and delays.
- October — complete the applicable assessment or notified-body review; check the current Official Journal references rather than assuming a draft standard gives a presumption of conformity.
- November — close gaps and reconcile the technical file, EU declaration of conformity and CE placement. Do not claim readiness with an incomplete assessment.
- December — run the release gate before placing an in-scope product on the market; hold launch if there is no basis for the declaration and CE marking. Maintain support, monitor risks and log change decisions after release.